Question: The following information is given below about a project. begin { tabular } { | c | c | c | c | c
The following information is given below about a project.
begintabularccccccc
hline multirowtActivity & Optimistic Time weeks & begintabularl
Most
Likely Time weeks
endtabular & Pessimistic Time weeks & Expected Time weeks & Variance & multirowtImmediate Predecessors
hline & a & m & b & t & sigma &
hline A & & & & & &
hline B & & & & & & A
hline C & & & & & & A
hline D & & & & & & B
hline E & & & & & & D C
hline F & & & & & & C
hline G & & & & & & F
hline H & & & & & & F
hline I & & & & & & E G H
hline J & & & & & & I
hline
endtabular
a Determine the expected activity time t and variance leftsigmaright for each activity. Draw the network diagram using the expected times and the precedence information in the above table. b Determine the Earliest Start ES Earliest Finish EF Latest Start LS Latest Finish LF and Slack values for each activity, and complete the table below.
begintabularcccccc
hline Activity & begintabularc
Earliest
Start
endtabular & begintabularc
Earliest
Finish
endtabular & begintabularc
Latest
Start
endtabular & begintabularc
Latest
Finish
endtabular & Slack
hline A & & & & &
hline B & & & & &
hline C & & & & &
hline D & & & & &
hline E & & & & &
hline F & & & & &
hline G & & & & &
hline H & & & & &
hline I & & & & &
hline J & & & & &
hline
endtabular
c Determine the critical path for this project. Calculate the expected project duration and standard deviation. Then use the zscore table attached on the next page of this assignment to determine the probability that the project will be completed within weeks. The following information is given below about a project.
begintabularccccccc
hline multirowtActivity & Optimistic Time weeks & begintabularl
Most
Likely Time weeks
endtabular & Pessimistic Time weeks & Expected Time weeks & Variance & multirowtImmediate Predecessors
hline & a & m & b & t & sigma &
hline A & & & & & &
hline B & & & & & & A
hline C & & & & & & A
hline D & & & & & & B
hline E & & & & & & D C
hline F & & & & & & C
hline G & & & & & & F
hline H & & & & & & F
hline I & & & & & & E G H
hline J & & & & & & I
hline
endtabular
a Determine the expected activity time t and variance leftsigmaright for each activity. Draw the network diagram using the expected times and the precedence information in the above table.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
