Question: If the optimistic time for an activity is 6 weeks, the pessimistic time is 24 weeks and the most likely time is 12 weeks, then

If the optimistic time for an activity is 6
If the optimistic time for an activity is 6 weeks, the pessimistic time is 24 weeks and the most likely time is 12 weeks, then the expected duration is (Assuming Beta distribution): 09 weeks O 13 weeks 12.5 weeks O 14 weeks 11 weeks