Question: If you know that an activity on the critical path has a latest finish time of 1 2 weeks and the activitytakes 5 weeks to

If you know that an activity on the critical path has a latest finish time of 12 weeks and the activitytakes 5 weeks to complete, then the earliest finish time is ________ weeks