Question: If you know that an activity on the critical path has a latest finish time of 1 2 weeks and the activitytakes 5 weeks to
If you know that an activity on the critical path has a latest finish time of weeks and the activitytakes weeks to complete, then the earliest finish time is weeks
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
