Question: ify GE - - - 5 1 0 3 - 2 P 2 - SP - 2 0 2 3 [ Based on Project Management

ify
GE---5103-2P2-SP-2023[Based on Project Management Professional (PMP) Based on PMBOK7]
Which of the following statements is not true regarding the relationship between project deliverables, delivery cadence, development approach, and project life cycle?
C
D
These relationships can change during the project as feedback is received and new understandings are gained.
There are no standard project life cycle phases. Project life cycles and phases are dependent on industry, organization, number of deliverables, development approach, and delivery cadence.
The project life cycle and phases should connect delivery of business and stakeholder value from the beginning to the end of the project.
A project life cycle cannot include multiple development approaches and delivery cadences.
The project life cycle phases should facilitate the development approach and delivery cadence required.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!