Question: Immediate Predecessor(s) Activity A B C MOOL LLUI-> Activity Time (days) 1 3 5 3 1 9 2 4 5 5 A A B B

Immediate Predecessor(s) Activity A B C MOOLImmediate Predecessor(s) Activity A B C MOOL

Immediate Predecessor(s) Activity A B C MOOL LLUI-> Activity Time (days) 1 3 5 3 1 9 2 4 5 5 A A B B , DE F F G, HI J b. Calculate the critical path for this project. The critical path is A-C-F-I-J and the project duration is 25 days. (Enter your response as a whole number.) c. How much slack is in each of the activities G, H, and I? Activity Activity Time (days) 2 On critical path? Slack (days) G No H 4 No 1 5 Yes Enter your answer in the edit fields and then click Check