Question: Immediate Predecessors Time (in hours) Activity A B D E F G 6.0 7.2 5.0 6.0 4.5 7.7 4.0 A B, C B,C D E,

Immediate Predecessors Time (in hours) Activity A

Immediate Predecessors Time (in hours) Activity A B D E F G 6.0 7.2 5.0 6.0 4.5 7.7 4.0 A B, C B,C D E, F a) Draw the project network using AON. b) Identify the critical path. c) What is the expected project length? d) Draw a Gantt chart for the project. P