Question: .. 3.7 Task time estimates for a production line setup project at Robert Klassen's Ontario factory are as follows: Immediate Predecessors Time (in hours) Activity

.. 3.7 Task time estimates for a production line
.. 3.7 Task time estimates for a production line setup project at Robert Klassen's Ontario factory are as follows: Immediate Predecessors Time (in hours) Activity A OLU D E 6.0 7.2 5.0 6.0 4.5 7.7 4.0 A B, C B, C D E, F G a) Draw the project network using AON. b) Identify the critical path. c) What is the expected project length? d) Draw a Gantt chart for the project

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!