Question: In a $ 2 0 , 0 0 0 , 0 0 0 contract the Contractor walks away half way through the project. The Contractor

In a $20,000,000 contract the Contractor walks away half way through the project. The Contractor to date has received $12,000,000. The Owner is forced to hire a new contractor to complete work at a total of $18,000,000. Therefore the total cost of construction is $30,000,000.
With a 100% face value for the Performance bond, the bonding company will pay the Owner
Question Blank 1 of 2
18,000,000
dollars for the damages incurred on the project and the owner will be able to recover
Question Blank 2 of 2
0
dollars from the contractor.