Question: In a batch machining operation, setup time is 50 min and batch size is 70 units. The cycle time consists of part handling time of
In a batch machining operation, setup time is 50 min and batch size is 70 units. The cycle time consists of part handling time of 25 sec and processing time of 1.3 min. One part is produced each cycle. Tool changes must be performed every 10 parts and this takes 1.0 min. Determine the average production rate.