Question: In a CPM network, the critical path has four activities as tabulated below: Complete the table and compute the following: a . The expected mean

In a CPM network, the critical path has four activities as tabulated below:
Complete the table and compute the following:
a. The expected mean time (in days) for the project completion: days
b. The estimated variance (in days) for the project: days
c. The estimated standard deviation (in days) for the critical path completion time: days
d. The probability that the critical path for this project will be completed within 70 days: % 
(Refer to the attached normal distribution table)