Question: In a CPM network, the critical path has four activities as tabulated below: Complete the table and compute the following: a . The expected mean
In a CPM network, the critical path has four activities as tabulated below:
Complete the table and compute the following:
a The expected mean time in days for the project completion: days
b The estimated variance in days for the project: days
c The estimated standard deviation in days for the critical path completion time: days
d The probability that the critical path for this project will be completed within days: 
Refer to the attached normal distribution table
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
