Question: Based on a 52 week latest that the project can be calculated, I want to calculate LS and LF Duration ES EF LS LF Predecessor

Based on a 52 week latest that the project can be calculated, I want to calculate LS and LF

DurationESEFLSLFPredecessor
A303 None
B3.536.5 A
C336 A
D7.5613.5 B,C
E713.520.5 D
F21.6666720.542.16667 E
G2.33333335.333333 A
H15.36.3 G
I96.315.3 H
J1513.528.5 D
K4.83333320.525.33333 E
L725.3333332.33333 J,K
M732.3333339.33333 L
N739.3333346.33333 M
O246.3333348.33333 N
P9.33333315.324.63333 I