Question: Based on a 52 week latest that the project can be calculated, I want to calculate LS and LF Duration ES EF LS LF Predecessor
Based on a 52 week latest that the project can be calculated, I want to calculate LS and LF
| Duration | ES | EF | LS | LF | Predecessor | |
| A | 3 | 0 | 3 | None | ||
| B | 3.5 | 3 | 6.5 | A | ||
| C | 3 | 3 | 6 | A | ||
| D | 7.5 | 6 | 13.5 | B,C | ||
| E | 7 | 13.5 | 20.5 | D | ||
| F | 21.66667 | 20.5 | 42.16667 | E | ||
| G | 2.333333 | 3 | 5.333333 | A | ||
| H | 1 | 5.3 | 6.3 | G | ||
| I | 9 | 6.3 | 15.3 | H | ||
| J | 15 | 13.5 | 28.5 | D | ||
| K | 4.833333 | 20.5 | 25.33333 | E | ||
| L | 7 | 25.33333 | 32.33333 | J,K | ||
| M | 7 | 32.33333 | 39.33333 | L | ||
| N | 7 | 39.33333 | 46.33333 | M | ||
| O | 2 | 46.33333 | 48.33333 | N | ||
| P | 9.333333 | 15.3 | 24.63333 | I |