Question: In a MRP problem, A is a MPS item. Every A requires 2 Bs and 3 Cs. Every B requires 5 Cs. All lead times
In a MRP problem, A is a MPS item. Every A requires 2 Bs and 3 Cs. Every B requires 5 Cs. All lead times are two periods. All initial inventory values are 0. Use lot-for-lot method for order quantities for all items. What is the low level code (LLC) for B and C