Question: In a MRP problem, A is a MPS item. Every A requires 2 B ' s and 3 C ' s . Every B requires

In a MRP problem, A is a MPS item. Every A requires 2 B's and 3 C's. Every B requires 5 C's. All lead times are two periods. Initial inventory values for A is
100,B is 200 and C is 0. Use lot-for-lot method for order quantities for all items. If gross requirement for A is 800 in period 9, what will be the planned
order release for B in period 5?
Multiple Choice
800
1,600
1,200
1,400
700