Question: In a particular project, activity C and activity D both immediately follow activity B. For C: ES-16, LS-17 For D: ES-19, LS-23 The latest finish

In a particular project, activity C and activity
In a particular project, activity C and activity D both immediately follow activity B. For C: ES-16, LS-17 For D: ES-19, LS-23 The latest finish (LF) for activity B is: 42 33 23 17