Question: In a PERT problem our project has an expected completion time of 2 0 0 days and a standard deviation of 1 1 days. What

In a PERT problem our project has an expected completion time of 200 days and a standard deviation of 11 days. What is the probability of us finishing in 222 days or sooner?
The normal curve data that we have been using comes from the chart on page 866(Table A in Appendix B).
Group of answer choices
95.8%
97.7%
98.3%
98.9%
99.2%