Question: In a PERT problem our project has an expected completion time of 8 0 days and a standard deviation of 3 days. What is the
In a PERT problem our project has an expected completion time of days and a standard deviation of days. What is the probability of us finishing in days or sooner?
The normal curve data that we have been using comes from the chart on page Table A in Appendix B