Question: Problem 4 : A project has an expected completion time of 40 weeks and a standard deviation of 5 weeks. It is assumed that the

Problem 4

: A project has an expected completion time of 40 weeks and a standard deviation of 5 weeks. It is assumed that the project completion time is normally distributed.

(a) What is the probability of finishing the project in 50 weeks or less?

(b) What is the probability of finishing the project in 38 weeks or less?

(c) The due date for the project is set so that there is a 90% chance that the project will be finished date?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!