Question: In a PERT problem our project has an expected completion time of 200 days and a standard deviation of 11 days. What is the probability
In a PERT problem our project has an expected completion time of 200 days and a standard deviation of 11 days. What is the probability of us finishing in 222 days or sooner?
95.8%
97.7%
98.3%
98.9%
99.2%