Question: In a sequential batch machining operation, setup time is 1 . 9 hours and batch size is 2 3 9 units. The cycle time consists

In a sequential batch machining operation, setup time is 1.9 hours and batch size is 239 units. The cycle time consists of part handling time of 34 sec. and processing time of 3.16min. One part is produced each cycle. Tool changes must be performed every 14 parts and this takes 2.3min. Determine the average production rate (pchr)(answer to 2 decimal points).