Question: In a sequential batch machining operation, setup time is 2.2 hours and batch size is 188 units. The cycle time consists of part handling time

In a sequential batch machining operation, setup time is 2.2 hours and batch size is 188 units. The cycle time consists of part handling time of 33 sec. and processing time of 3.43 min. One part is produced each cycle. Tool changes must be performed every 9 parts and this takes 2.1 min. Determine the average production rate (pc/hr)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!