Question: In _ _ _ _ , all the resources needed to accomplish each project are assigned full - time to work on that project. a

In ____, all the resources needed to accomplish each project are assigned full-time to work on that project.
a.
a project management office
b.
an autonomous project organizational structure
c.
a functional organizational structure
d.
a matrix organizational structure