Question: In an MRP problem, A is an MPS item. Every A requires 3 B's and 2 C's. Every B requires 5 C's. All lead times
In an MRP problem, A is an MPS item. Every A requires 3 B's and 2 C's. Every B requires 5 C's. All lead times are one period. Initial inventory values for all items are 0. Use lot-for-lot method for order quantities for all items. If gross requirement for A is 400 in period 10, what will be the planned order release for C in period 8?
| A. | 1,600 | |
| B. | 800 | |
| C. | 1,200 | |
| D. | 6,800 | |
| E. | 6,000 |