Question: In an MRP problem, A is an MPS item. Every A requires 3 Bs and 2 Cs. Every B requires 5 Cs. All lead times
In an MRP problem, A is an MPS item. Every A requires 3 Bs and 2 Cs. Every B requires 5 Cs. All lead times are one period. Initial inventory values for all items are 0. Use lot-4-lot method for order quantities for all items. If gross requirement for A is 400 in period 10, what will be the planned order release for C in period 8?
Multiple Choice
-
800
-
1600
-
6800
-
6000
-
1200