Question: Question 1 7 In an MRP problem, A is an MPS item. Every A requires 3 B s and 2 C s . Every B

Question 17
In an MRP problem, A is an MPS item. Every A requires 3 B s and 2 C s. Every B requires 5 C s. All lead times are one period. Initial inventory values for all items are 0. Use lot-4-lot method for order quantities for all items. If gross requirement for A is 400 in period 10, what will be the planned order release for C in period 8?
800
1600
6800
6000
1200