Question: In developing the project plan Fazila realizes that for tasks that have multiple resources, not all resources are required to start working on a specific

In developing the project plan Fazila realizes that for tasks that have multiple resources, not all resources are required to start working on a specific task at the same time. Thus, Fazila is considering delaying the start of assignments for specific resources. In doing so Fazila must keep in mind that:

The critical path of the plan may change.

The other resources assigned to the task are also affected.

The labour cost of the task is affected.

The cost of material resources based on variable-rate quantity is not affected.