Question: In developing the project plan Fazila realizes that for tasks that have multiple resources, not all resources are required to start working on a specific
In developing the project plan Fazila realizes that for tasks that have multiple resources, not all resources are required to start working on a specific task at the same time. Thus, Fazila is considering delaying the start of assignments for specific resources. In doing so Fazila must keep in mind that:
| The critical path of the plan may change. | |
|
| The other resources assigned to the task are also affected. |
|
| The labour cost of the task is affected. |
|
| The cost of material resources based on variable-rate quantity is not affected. |