Question: In earned value analysis, it was found that: BCWP = $ 3 0 , 1 0 0 , BCWS = $ 2 9 , 5
In earned value analysis, it was found that: BCWP $ BCWS $ and ACWP $ The project is:
Question options:
a
Ahead of schedule and overbudget.
b
Ahead of schedule and underbudget.
c
Behind schedule and overbudget.
d
Behind schedule and underbudget.