In earned value analysis, it was found that: BCWP = $30,100, BCWS = $29,500, and ACWP = $31,200. The project is:
Question 29 options:
a)
Ahead of schedule and overbudget.
b)
Ahead of schedule and underbudget.
c)
Behind schedule and overbudget.
d)
Behind schedule and underbudget.