Question: In making a forward pass through a network, activities L, M, and P are immediate predecessors for activity T, which has an activity time of

In making a forward pass through a network,
In making a forward pass through a network, activities L, M, and P are immediate predecessors for activity T, which has an activity time of 13. The early start times for activities L, M, and Pare 22, 17, and 27, respectively. The early finish times for activities L, M, and Pare 29, 27, and 33, respectively. What is the early finish time for activity T? 42 40 44 46 38