Question: In MRP processing the difference between a planned-order release and the planned-order receipt is: a. the level of net requirements. b. level of safety stock.
In MRP processing the difference between a planned-order release and the planned-order receipt is:
a. the level of net requirements.
b. level of safety stock.
c. timing as per the lead time.
d. a one is a forecast and the other is actual.
e. scheduled receipts of open orders.