Question: In project management, the difference between CPM and PERT is that Group of answer choices CPM is used when the order of activities are known,

In project management, the difference between CPM and PERT is that

Group of answer choices

CPM is used when the order of activities are known, and PERT is used when the order of activities is uncertain

PERT is used when activity times are known, and CPM is used when activity times are uncertain

CPM is used when activity times are known, and PERT is used when activity times are uncertain

PERT is used when the order of activities are known, and CPM is used when the order of activities is uncertain