Question: In scheduling, when we use the average tardy metric to choose between priority rules, we prioritize the job order which has _______per job. a) highest
In scheduling, when we use the average tardy metric to choose between priority rules, we prioritize the job order which has _______per job.
a) highest average processing time
b) largest average number of customers
c) smallest average revenue
d) smallest average lateness