In the SohnCo Baby Products Division plant located in New Brunswick, NJ, one Baby Mobile is assembled
Fantastic news! We've Found the answer you've been seeking!
Question:
In the SohnCo Baby Products Division plant located in New Brunswick, NJ, one Baby Mobile is assembled from the following:
A36 4
B22 2
C35 1
A B22 requires 1 C7 and a purchased D 19. All A parts are made in Department 2979, B parts are made in Department 4330, and C parts are made in department 2976. Lead times are set at one week. An A 36 requires 2.5 hours. A B22 requires 3 hours. All other parts require 0.5 hour per part of time. Develop a capacity load profile for this plant.