Question: In the table below you will find the task involved in a production process where each and every other task is completed based on the
In the table below you will find the task involved in a production process where each and every other task is completed based on the completion of the other task. The final step completed is on Task M. Based on the chart, give the answers below:
| Task | Time (in minutes) | Task must complete |
| A | 0.5 | - |
| B | 1.0 | A |
| C | 2.2 | B |
| D | 2.3 | A |
| E | 0.5 | B |
| F | 3.2 | D |
| G | 0.5 | C |
| H | 0.6 | E |
| I | 0.2 | E |
| J | 0.2 | G |
| K | 1.2 | H,J |
| L | 3.2 | F,I |
| M | 0.0 | K,L |
Show the Precedence Graph that we learnt in class for the above production process.
Find out what is the lowest time required to have efficient performance in the production process.