Question: In the Task Information dialog box below, what does the -2d for #7 Task mean? Task Information General Predecessors Resources Advanced Notes Custom Fields Duration:

In the Task Information dialog box below, what
In the Task Information dialog box below, what does the "-2d" for #7 Task mean? Task Information General Predecessors Resources Advanced Notes Custom Fields Duration: 15 days Estimated Name: Copyedit Predecessors ID Task Name 7 Organize manuscript for copyedit Type Finish-to-Start (FS) Lag -20 Help OK Cancel It has 2 days of Lead. It has 2 days of Lag. It is the second task to schedule. It needs to be crashed for 2 days