Question: In the website development project network shown in the following figure, the number alongside each activity designates the activity duration ( TE ) in weeks.
In the website development project network shown in the following figure, the number alongside each activity designates the activity duration TE in weeks.
Determine:
a The ES and LS for each activity.
b The earliest time that the website can be completed.
c The slack on all activities.
d The critical activities.
e The critical path.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
