Question: In the website development project network shown in the following figure, the number alongside each activity des - ignates the activity duration ( TE )

In the website development project network shown in the
following figure, the number alongside each activity des-
ignates the activity duration (TE) in weeks.
Determine:
(a) The ES and LS for each activity.
(b) The earliest time that the website can be completed.
(c) The slack on all activities.
(d) The critical activities.