Question: In this assignment, take the following work breakdown structure and organize it into a CPM Chart. The estimated time, is measured in days, and they
In this assignment, take the following work breakdown structure and organize it into a CPM Chart.
The estimated time, is measured in days, and they appear in the boxes in the bottom right corner of each task.
For the purpose of having dependencies, the design for a feature must be complete before programming for that feature can occur. The feature design must also be complete before the user manual can be written for that feature. You must program the home page, before you program the search bar. The programming for the search bar and homepage does not need to be completed before you connect the database to the application these can be done in parallel The programming for a feature must be complete AND the database must be connected to the application before you can execute acceptance tests.
The programming for the database must be complete before you can connect the database to the application. You can test the database after the database is connected to the application.
For simplicity, you can combine all the acceptance tests tasks to one line named Execute Acceptance Tests on All Pages that takes day to complete.
You can create the CPM Chart for the product using any program that you wish. You may also choose to draw the CPM Chart by hand.
Upload your finished CPM Chart to Coursera. Please submit your CPM Chart as a JPEG, PNG or PDF file type.
Grading Criteria Overview
ReplyForward
Add reaction
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock