Question: In this exercice, we are required to complete a statement about the use of schedule and cost indexes over the absolute values of SV and
In this exercice, we are required to complete a statement about the use of schedule and cost indexes over the absolute values of SV and CV
Let's start by understanding those concepts:
The Schedule Performance Index is calculated by dividing the Earned Value EV by the Planned Value PV The SPI represents the efficiency of the project in terms of schedule.
The Cost Performance Index is calculated by dividing the Earned Value EV by the Actual Cost AC The CPI represents the efficiency of the project in terms of cost
Indeed, practitioners sometimes prefer to use schedule and cost indexes over the absolute values of SV and CV because indexes are considered efficiency ratios.
Efficiency ratios provide a measure of how effectively resources are being utilized to achieve project objectives.
In conclusion, indexes are preferred because they offer better insights on the efficiency.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock