Question: is there a cost overrun or cost underrun? Please study the Actual Cost Table below. b. What is the Cumulative Actual Cos ANSWER: The cumulative
is there a cost overrun or cost underrun?

Please study the Actual Cost Table below. b. What is the Cumulative Actual Cos ANSWER: The cumulative actual cost is 158 Week 1=17,000 Week 2=40,000 Please study the Budgeted Cost Table below. a. What is the cumulative budgeted costs (CBC) at the end of week 6 ? ANSWER: The CBC at the end of week 6 is 142,000 . week 1=15,000 Week 2=34,00 Week 3=28,000 Editor. Check for Spelling, Grammar, a Writing Issues