Question: ITPM Find Critical Path A 07 7 2 9 C 7 19 12 14 26 F 26 32 6 26 32 Start Finish B 09

 ITPM Find Critical Path A 07 7 2 9 C 7

ITPM

Find Critical Path A 07 7 2 9 C 7 19 12 14 26 F 26 32 6 26 32 Start Finish B 09 9 09 D 9 17 8 9 17 E 17 26 9 17 26 G 26 31 5 27 32 Select one a. Start,A,C,F. Finish b. Start A,D,E,F, Finish c. Start A,DEG, Finish O d. Start,B,D,E,F, Finish Which of the following is a characteristic of a scope statement? Select one a. Defines the baseline for project acceptance b. Defines the requirements for each project c. Defines the cost, schedule, and quality metrics d. None