Question: In the following table, task durations are given in weeks. The estimates were made at the 95 percent level (Calculating Probabilistic Activity Times subsection). a.
In the following table, task durations are given in weeks. The estimates were made at the 95 percent level (Calculating Probabilistic Activity Times subsection).
.png)
a. Find the expected time and variance for each task.
b. Draw the network (either AOA or AON) and find the critical path and time.
c. Find the probability that the critical path will be completed in 23 weeks.
d. Find the probability that the other main paths will be completed in 23 weeks.
e. What is the probability that the entire network will be completed in 23weeks?
ss |6970788 4556545 P2344433 aa,de abcdefg
Step by Step Solution
3.32 Rating (152 Votes )
There are 3 Steps involved in it
a The spreadsheet below can be used to calculate the expected time and variance for each activity b ... View full answer