In the following table, task durations are given in weeks.


a. Find the expected time and variance for each task.
b. Draw the network (either AOA or AON) and find the critical path and time.
c. Find the probability that the critical path will be completed in 23 weeks.
d. Find the probability that the other main paths will be completed in 23 weeks.
e. What is the probability that the entire network will be completed in 23weeks?

ss |6970788 4556545 P2344433 aa,de abcdefg

Step by Step Solution

3.32 Rating (152 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a The spreadsheet below can be used to calculate the expected time and variance for each activity b ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

132-B-M-L-P-M (1042).docx

120 KBs Word File

Students Have Also Explored These Related Management Leadership Questions!