Question: Jake is working on his project plan, and adding resources to it . He needs to add rented equipment and some temporary staffing. Which type
Jake is working on his project plan, and adding resources to it He needs to add rented equipment and some temporary staffing. Which type of resource is he adding, and what is true about the cost?Select an answer:He is adding the cost resource. He should apply the cost when he assigns the cost resource.He is adding the project resource. The costs will not affect the project.He is adding the work resource. The costs will affect the labor cost for the project.He is adding the material resource. He should add the quantity and cost per unit.