Question: Jamison Construction has implemented a cost estimation system using regression analysis. The variable cost per hour of labor is $20 and the fixed cost was
Jamison Construction has implemented a cost estimation system using regression analysis. The variable cost per hour of labor is $20 and the fixed cost was determined to be $220,000. If Jamison projects it will be working 253,000 hours in 2019, what is the projected total cost?
Step by Step Solution
There are 3 Steps involved in it
Solution To find the projected total cost for Jamison Construction we c... View full answer