Question: Job A, B, C, D, E with processing times (days): 8, 2, 4, 6, 7 and immediate predecessors are -, A, B, B, and C
Job A, B, C, D, E with processing times (days): 8, 2, 4, 6, 7 and immediate predecessors are -, A, B, B, and C & D. Determine the critical path for this project.
a. A-B-C-D-E
b. A-B-D-E
c. A-B-C-E
d. B-C-D-E
Job A, B, C, D, E with processing times (days): 8, 2, 4, 6, 7 and immediate predecessors are -, A, B, B, and C & D. What is the earliest completion time of D?
a.14
b.10
c.16
d.11