Question: Job A, B, C, D, E with processing times (days): 8, 2, 4, 6, 7 and immediate predecessors are -, A, B, B, and C

Job A, B, C, D, E with processing times (days): 8, 2, 4, 6, 7 and immediate predecessors are -, A, B, B, and C & D. Determine the critical path for this project.

a. A-B-C-D-E

b. A-B-D-E

c. A-B-C-E

d. B-C-D-E

Job A, B, C, D, E with processing times (days): 8, 2, 4, 6, 7 and immediate predecessors are -, A, B, B, and C & D. What is the earliest completion time of D?

a.14

b.10

c.16

d.11