Question: John is the Project Manager for a an Application development project. The time duration for the project as agreed upon with all the Stakeholders is
John is the Project Manager for a an Application development project. The time duration for the project as agreed upon with all the Stakeholders is months. The allocated budget for the project is $ This budget is expected to be evenly distributed during the life of the project. The project has just completed months and entered th month of execution. At the end of months, the actual cost incurred on the project is $ and the project is complete.
Is this project behind schedule?
True
False