Question: John is the Project Manager for a an Application development project. The time duration for the project as agreed upon with all the Stakeholders is

John is the Project Manager for a an Application development project. The time duration for the project as agreed upon with all the Stakeholders is 12 months. The allocated budget for the project is $600,000. This budget is expected to be evenly distributed during the life of the project. The project has just completed 3 months and entered 4th month of execution. At the end of 3 months, the actual cost incurred on the project is $175,000 and the project is 30% complete.
Is this project behind schedule?
True
False
 John is the Project Manager for a an Application development project.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!