Question: K Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be
K Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: Activity Immediate Predecessor(s) Time (days) A B 2 5 1 D B 10 E A, D 5 F C 5 G E, F 8 This exercise contains only parts b, c, and d. b) The critical activities for the leadership training program development project are B-D-E-G c) The project length for the leadership training program development project 28 days. d) Slack time for each of the activities is: Activity Slack Time Incorrec