Question: Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before
Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table:
.png)
a) Develop an AON network for this problem.
b) What is the critical path?
c) What is the total project completion time?
d) What is the slack time for each individual activity?
IMMEDIATE ACTIVITY PREDECESSOR(S) TIME (DAYS) I) 10 A, D 8
Step by Step Solution
3.40 Rating (169 Votes )
There are 3 Steps involved in it
a AON diagram of the project b The critical path listing all critical activities in chron... View full answer