Question: k The following table lists the components needed to assemble an end item, lead times, and quantities on hand. End C F G H Item
k The following table lists the components needed to assemble an end item, lead times, and quantities on hand. End C F G H Item LT (week) 3 3 3 31 Amount on hand 0 27 0 Click here for the Excel Data File End Hum B C25 DI E (2) FO) Gai E12 HMI E (2) a. If 23 units of the end item are to be assembled, how many additional units of E are needed? (Hint. You don't need to develop an MRP plan to determine this) Additional units b. An order for the end item is scheduled to be shipped at the start of week 18. What is the latest week that the order can be started and still be ready to ship on time? (Hint You don't need to develop an MRP plan for this part either) The latest week 842 437 B 12 032 E23 D 525 OWI