Question: Layout Site ( Civil ) - 1 week to complete Layout Process Piping and Equipment ( Mechanical ) - 2 weeks to complete Layout Building
Layout Site Civil week to complete
Layout Process Piping and Equipment Mechanical weeks to complete
Layout Building Architectural weeks to complete
Structural Building Design Structural weeks to complete
Mechanical Systems Design weeks to complete
Electrical Systems Design weeks to complete
InternalExternal Review week to complete
You may pick your own dollar amounts as to the cost of each deliverable listed above in preparing the cumulative cost curve for the lift station as you will for the individual project.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
