Question: eclass.al Given the following table: Activity Predecessor Time Cost Normal Crashed Normal Crashed A 14 10 20000 26000 B A 18 14 25000 33000 B

eclass.al Given the following table: Activity

eclass.al Given the following table: Activity Predecessor Time Cost Normal Crashed Normal Crashed A 14 10 20000 26000 B A 18 14 25000 33000 B 16 12 30000 40000 15 12 30000 39000 E D 15 12 17000 27000 F E 15 11 23000 39000 G 13 12 50000 56000 H 0 17 16 40000 45000 0 H 12 12 45000 45000 LIVE The normal time and the normal cost of the project. (2m) 2. The crashed time of the project (1 m) 3. Fill template 1 (slopes), (4 m) The crashed cost of the project using method one, by filling template 2_(Zm)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!