Question: include the drawing of normal time and crashed time Given the following table: Activity Predecessor Time Cost Normal Crashed Normal Crashed W | 16 13

include the drawing of normal time and crashed

include the drawing of normal time and crashed time

include the drawing of normal time and crashedinclude the drawing of normal time and crashed

Given the following table: Activity Predecessor Time Cost Normal Crashed Normal Crashed W | 16 13 20000 26000 B A 16 10 25000 43000 IC B 15 10 30000 50000 15 14 30000 31000 D 14 10 17000 25000 E 15 13 23000 29000 14 13 50000 53000 G 14 12 40000 48000 J H 13 11 45000 55000 1. The normal time and the normal cost of the project. (2m) 2. The crashed time of the project (1m) 3. Fill template 1 (slopes), (3m) 4. The crashed cost of the project using method one, by filling template 2_(7m). 5. The crashed cost of finishing the project in 41 days, by filling template 3 (7m) Template 1 Activity Slope A B G H Template 2 Activity Early Early Late Late TF Relax by Savings Start Finish Start Finish Template 3 Additional cost Total cost Time of Critical path the project What activity to crash, and by how much

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!